My Home Construction Projects Over The Years

 


North Lauderdale Home Projects

1980 - 35 years Old

"We now had 3 children and after Commuting to work for 4 years
in Ft Lauderdale from West Palm Beach and Stating a New Job as
a Cad Manager with Motorola in Plantation, It was Time to Move."

As my luck Goes, This was a Expensive time to Move, We
Sold the House for $35,000 and Rented a apartment in the
the North Lauderdale Area for about 8 months. During this
period of time Home prices doubled and interest rates shot
to an unbelievable 17% ! We Found a New 3/2 - 1 car garage
Home already built, in the unfinished development called "The
Fountains of Tam O'Shanter" for sale for $70K. I bargained
with the Builder, finally got it for $65K, because the original
buyer could not buy it at the higher interest rate.

I would later refinance it down to a more reasonable rate !


 

 Well a few months after moving into our new 3/2 house,
We get word that my Wife's Brother Khanh, who had escaped
from then Communist Vietnam to Singapore, Needed a family
to Sponsor him so he could come to the United States to live..

So, Of Course I said Yes to the Wife

Khanh Doing a Little Wax On and Wax Off

"So Out come the Hammers and Saws Again..
We were one Bedroom Short again !"

The development was only about half finished at this time,
so I took my Camera, Tape measure, Notebook and Pen to
document the proper way of Constructing the Wood frame
 stucco addition that I wanted to build. The house we bought
was idea to add on to... No accident.. I knew some day I would.

 

First, a Little Stucco Frame House Construction 101

First, Find a House the same as Mine under construction !
Walk through it, take pictures, make notes ..Then

 

Now, Find Same at start of Construction, for Bolt Placement

 

Placement of Footer Wall 2x4's

 

Now, Lets see how you Join the walls at the Corners

 

A Single Door Framing

 

A Sliding Glass Door Framing

 

Regular Double 30X48 Window Framing Opening

 

   

Single 30X48 Window                   Double 30X48 Window

 

Large Front Windows, Entry Door, Garage Door Framing

 

Now Time for some Inside Load Bearing Wall Framing

 

 

 

 

 

 

 

End of a  Little Stucco Frame House Construction 101


Let the Fun Begin Again

Well, You Notice all the Construction Material that I am
Packing into the Garage ... Building Plans done, Approved
and City Building Permits in hand.

Starting digging for the Foundation

 

Khanh wants a Bedroom so He helps me on this project

 

Taking a break after Pulling Fence out for now

 

Forming up the Foundation

 

Ground Termite Treated, Moisture Barrier, Wire and Rods in

 

Before Pulling out the Fence so the Concrete Truck
can get between the houses to pour my foundation.

 

Foundation Poured and Finished.. Almost lost the Second
Concrete Delivery Truck in the Canal !

Starting the Wall Framing

 

The Middle, Load bearing wall Up

 

Putting in the Roof Beams in the First Section

 

Putting in the Roof Beams to the Outside wall

 

 

 

 

Roof Finished

 

Time to Start the Stucco Process on the outside Walls

 

Tar Paper and Wire Lath Finished

 

I have finished Stuccoing All the Outside Walls

 

 

 

Outside Walls Finished with First Coat of Paint.

 

 


 

Before I can finish the Addition .. We need a Bigger Driveway

 

 

 

Khanh's Brown Comet

 

 

 

 

 

 

Two of My Helpers

 

Time to Finish Painting the Front of the House

Finally after 2 years .. Addition, Driveway, and Painting Finished !

 


Next House Project

My Sunrise, FL Home addition Project

 

 

Copyright 2009 -   www.BobShermansPage.com -  All Rights Reserved.